Contact the safety measures of the old road in Shangshan

Contact the safety measures of the old road in Shangshan

19# Coal contact Shangshan excavation construction process will encounter the old roadway in the past. Because the old roadway is closed for a long time, idle, no ventilation measures are adopted, it is easy to accumulate a large amount of gas, water and other toxic and harmful gases, and the oxygen content is small, in order to guarantee The safety of the old roadway construction is proceeding smoothly, and the following safety technical measures are formulated:

1. The geological survey personnel of the engineering and technical department must check in time to find out the location of the old lane, and clearly mark it on the map, and give the geological prediction and prediction.

2. The Ministry of Customs and Excise Department shall conduct drilling operations in time and carry out on-the-spot detection in advance. During the construction drilling, the inspectors of the tile shall, in addition to the normal working surface, be responsible for the concentration of toxic and harmful gases such as gas and carbon monoxide in the drilling port. Check at any time. If the concentration of toxic and harmful gases such as gas and carbon monoxide exceeds the relevant provisions of the “Safety Regulations for Coal Mines”, the drilling rig must be stopped, the power supply must be cut off, personnel should be withdrawn, and the mine dispatching room and relevant mine leaders should report back in time for timely treatment. .

3. Before the excavation, the 60m advanced exploration and drilling hole should be drilled along the direction of the excavation to further verify the position of the old lane and detect the detailed parameters of the old lane to confirm that there is no safety hazard.

4. When the distance from the old lane is 5m, the drilling hole should be constructed first, and the depth of the drilling should not be less than 5m, in order to accurately judge the position of the old lane and detect the water, gas and fire in the old lane to prevent blindly uncovering the old lane. Causing an accident. If there are pressures in the water, high concentration of gas and natural coal seams, you must stop the tunneling immediately and take measures to deal with it.

5, the old road support program

(1) Temporary support: After exposing the old lane, the team leader, security inspector, and tile inspector first enter the work surface to check the toxic and harmful gases. After knocking the top, the temporary pillars are set on the working surface.

Temporary support form and material specifications:

Temporary support frame shed using two metal beams before the probe, before the probe beam using two beam mine # 11, each of 4.2m length, each with three beams before the probe clip, evenly distributed, before the probe beam They are hung at 0.8m on both sides of the center of the shed beam. The method of using the front probe beam: a. When the front probe beam is first, the three clamps are evenly inserted on the frame beam at a spacing of 1.2m (2 sheds), and the front probe beam is placed on the scaffolding to place the front probe beam in the clip slot. Inside, put a good baffle and tighten the screws. When the upper beam is on each of the three people, the four people lift the beam, and the two get on the card, and the force is the same. b. When the front probe beam moves forward, there are 3 people at both ends of the front probe beam. The two loosen the screws and the four people tighten the beam body to prevent slipping and hurting people, and forcefully move forward 0.6m (a shed). First tighten the two screws on the front side, then remove the clips and screws on the back side, and insert and tighten the screws on the frame beam at a distance of 0.6m (one shed) from the front.

(2) Permanent support

The permanent support adopts trapezoidal steel shed support with 11# I-beam processing. The upper beam has a net width of 4000mm, the upper beam is 4200mm long, the shed leg is 2900m long, the shed leg is 15°, the shed is 600mm, and the back plate is 400mm. Specifications: length × width × thickness = 800mm × 70mm × 40mm, the laying of the whole section 6m × 1.2m woven mesh, stubble pressure of not less than 100mm, # iron wire connection 14, connected to a pitch less than or equal 200mm; steel frame after a good frame for each Shed 4 struts, struts Specifications: length × width × thickness = 580mm × 70mm × 70mm

After the blasting operation, the construction personnel must first carry out temporary support, first support the roof of the roadway, and formulate the support plan according to the stability of the roof of the old lane. The top is designed according to the original top design. The two gangs are designed according to the width of the old lane. It is well sealed to prevent air leakage and finally sprayed completely. The thickness of the spray is not less than 150mm.

6. Safety measures for “one pass and three defenses” in the old lane

(1) Safety measures for ventilation in old lanes

Air supply system: the original local ventilator press-in type air supply, double fan dual power supply, the air duct adopts anti-static flame-retardant air cylinder, the air cylinder mouth is no more than 10m from the working surface, and the old lane is exposed at any time according to the situation. The air duct ensures that harmful gases are not exceeded. The standby fan must be powered by different power sources. In the normal situation, the main fan is supplied with air. The standby fan can automatically switch after the main fan stops, ensuring continuous supply of air.

(2) If there is an increase in the amount of return air after the passage of the old lane, the personnel must be evacuated immediately, and the gas composition must be observed. If there is no abnormality after 30 minutes of continuous observation, the production can be resumed at the working surface. Temporary wind barriers shall be set up at the passing points as soon as possible to restore the airflow to normal. During the period, the number of gas inspections must be increased, and abnormalities are immediately removed.

(3) If the amount of return air decreases, stagnate, and reverse after the penetration, it indicates that the air leakage is serious in the old road. At this time, the air volume of the heading face must be continuously monitored, and a temporary wind barrier should be set at the through point to reduce the air leakage to maintain the normal air volume of the working face. Prevent harmful gases such as gas from exceeding the limit.

7. Measures to prevent gas, spontaneous combustion, and prevention of coal dust in the old lane:

(1) Staffing: During the old lane, the roadway must be equipped with a full-time tile inspector to check the gas concentration, coal dust, and spontaneous combustion.

(2) Monitoring and monitoring instrument configuration: must be equipped with optical gas evaluator, multiple gas detectors, oxygen concentration analyzer, carbon monoxide detector, gas power eliminator and gas sensor. All instruments must be qualified and regularly Calibration to ensure the accuracy and reliability of the instrument.

Use 2

These brush machines integrate the functions of drilling holes and tufting fibers together. On the basis of international cutting edge brush making technology and our own patented inventions, Haixing brush machines have been well recognized  in China and abroad. Modular designs are adopted, and all the key components are of famous brands, or imported products. PLC touch screen control, easy and quick brush programming, standardized components, optional brush platforms, enable a stable and easy operation, and a convenient maintenance. Every machine is dedicatedly manufactured to satisfy customers' high requirements of quality standard. And dust suction unit is included to remove dust and waste material and keep the machine clean.

Brush Drilling And Tufting Machine

Brush Drilling And Tufting Machine, Plastic Broom Making Machine, Brush Drilling Machine, Paint Brush Making Machine, Strip Brush Making Machine, Plastic Brush Making Machine, Cnc Brush Machine, Brush Equipment

Yangzhou Haixing CNC Brush Machine Co., Ltd. , https://www.brushmachine.nl